Wasaga Beach Twin-Pad Arena and Library | Athletic Business

1. Wasaga Beach Twin-Pad Arena and Library

Opened 2023

2 ice pads

$45.3M

Reported construction cost

The 117,000-square-foot facility includes two NHL-sized ice surfaces, a public library, indoor walking track, community hall, and a multipurpose arena suitable for events. The town's original overall budget was approximately $60 million, while the construction contract was about $44.6 million. This is a particularly useful comparison because the project includes substantial community amenities.

Town of Wasaga Beach project announcement

Burnaby's Rosemary Brown arena, rec centre to open in April  - Vancouver Is Awesome

2. Rosemary Brown Recreation Centre

Opened 2024

2 ice pads

$49.5M

Reported project cost

An approximately 8,547-square-metre twin-pad arena with spectator seating, multipurpose rooms, a skate shop and rooftop patio.

City of Burnaby

 

Seven Chiefs Sportsplex | TRADE WEST

3. 7 Chiefs Sportsplex and Chief Jim Starlight Centre

Opened 2019

2 indoor ice pads

$55.6M

Reported project cost

A major multipurpose sports complex featuring two NHL-sized indoor ice pads, an additional covered outdoor rink, a large field house, fitness facilities, an indoor running track, meeting rooms and event space.

7 Chiefs Sportsplex

 

 

North Bay’s new arena has a proposed name: WFCU Place - North Bay News

4. WFCU Place – Community Recreation Centre

Opened 2026

2 ice pads

$63M

Total project budget

A new recreation facility with two regulation ice pads, 14 dressing rooms, an indoor walking track, spectator seating and community meeting space. The City of North Bay reports that the project was delivered on time and on budget.

Official City of North Bay project page

Home | Cenovus Energy Hub

5. Cenovus Energy Hub

Opened 2025

2 indoor + 1 outdoor sheet

$101.3M

Reported project cost

A larger spectator and community facility with two indoor ice surfaces, an outdoor community rink, event space, fitness amenities and concessions.

City of Lloydminster

2. Additional projects worth investigating

Proposed facilities or projects that have not yet completed construction.

Facility

Ice capacity

Reported cost

Status and relevance

 

 

 

 

Northside Twin Arena

Alberta Major Projects

2

$50M

Under construction; includes an 8,000-square-foot community centre.

Glenmore Twin Arena

Calgary Newsroom

2

$85.6M

Under construction, expected completion in 2027; includes spectator and multipurpose amenities.

Langley Events Centre arena expansion

Township of Langley

+1

3 ice + 2 dry-floor arenas

$149M

Expected to open in 2026; a larger, stacked multi-arena complex.

Kamloops Multiplex

4 proposed

$140M

Concept-stage estimate, not a completed project; useful for comparing the potential scope of a four-pad facility at a similar budget.